Wide shot of containerized energy storage systems and solar installations deployed in a desert microgrid project in Chad.

    ⚙️ Case

    2025-05-22

1.5 MW PV + 4.2 MWh BESS for Chad's First Hybrid Solar Power Station

Am-Zoer, Wadi Fira, Chad

Commissioned:2025-05-22

Client:Solar Power Station

  • 1.5 MW

    Solar PV Capacity

  • 4.2 MWh

    LiFePO4 Battery Storage

  • 30-Day

    On-Site Deployment

  • Hybrid

    Solar + ESS System

Project Overview

As Chad's first hybrid solar power station, this project integrates 1.5 MW solar PV generation, 4.2 MWh LiFePO4 battery storage, and an intelligent EMS platform to deliver stable clean power for Am-Zoer, Wadi Fira.
Commissioned on May 22, 2025, the solar-plus-storage system was installed and put into operation within 30 days of on-site deployment. Designed for remote energy infrastructure, it stores daytime PV generation, supports controlled power dispatch, and reduces reliance on diesel-based electricity.
The project shows how a turnkey hybrid solar ESS solution can support rural electrification, off-grid power supply, energy independence, and long-term renewable energy access in regions with limited grid coverage.

Challenge & Solution

Project Challenges

  • Limited grid access and unstable electricity supply in remote rural communities
  • High diesel generator dependence for continuous power and nighttime electricity
  • Harsh site conditions with wide ambient temperatures from -30°C to 55°C
  • Complex coordination between solar PV, battery storage, grid connection, and generator backup

SUNPAL ESS Solution

  • 1.5 MW high-efficiency solar PV system using 650W double-glass bifacial N-Type TOPCon modules
  • 4.2 MWh LiFePO4 battery energy storage system for extended clean power availability
  • 500 kW PCS with grid-tied and off-grid switching for flexible hybrid power operation
  • Intelligent EMS for real-time monitoring, energy dispatch, and multi-source power management

Key Technical Specifications

ParameterSpecification
PV Capacity1.5 MW
PV Module650W Double-glass Bifacial N-Type TOPCon
Module Efficiency22.95%
Battery Capacity4.2 MWh
Battery ChemistryLiFePO4
Battery Rack716.8 V / 280 Ah
PCS / InverterMPS0500
PCS Rated Power500 kW
PCS Output Current720 A
Operating ModeGrid-tied / Off-grid Switching
Energy ManagementIntelligent EMS
Cooling SystemForced Air Cooling
Ingress ProtectionIP20
Operating Temperature-30°C to 55°C
System TypeModular Containerized Hybrid Solar + Storage System

Project Timeline

APR 24, 2025 | System Arrival
The complete solar PV modules, LiFePO4 battery storage system, PCS, EMS, and auxiliary equipment arrived at the Am-Zoer project site, officially starting the on-site deployment of this hybrid solar + BESS project.

APR 25, 2025 | Site Installation
SUNPAL ESS engineers began electrical installation, cabinet positioning, cable connection, and equipment integration, preparing the 1.5 MW PV and 4.2 MWh battery energy storage system for fast commissioning.

MAY 3, 2025 | System Integration
The PV array, battery storage, PCS, EMS, grid interface, and generator backup were connected into one coordinated hybrid power system for multi-source energy dispatch and rural electrification.

MAY 10, 2025 | Testing & Training
The engineering team completed functional testing, safety inspection, EMS verification, grid-tied/off-grid operation checks, and basic operation training for local project personnel.

MAY 22, 2025 | Project Commissioned
Chad’s 1.5 MW PV + 4.2 MWh hybrid solar storage system was officially commissioned after about 30 days of on-site installation, demonstrating SUNPAL ESS turnkey ESS delivery capability for remote energy projects.

Feedback from Client Project Director

"Congratulations to the SUNPAL ESS team. You did a great job on this hybrid solar storage project. The installation and commissioning went very well, and we are pleased to see the 1.5 MW PV + 4.2 MWh LiFePO4 battery storage system running successfully. We appreciate the hard work and technical support from your engineering team. We hope to win more renewable energy and BESS projects together and implement them successfully."

Project Information

  • Client:

    Solar Power Station

  • Location:

    Am-Zoer, Wadi Fira, Chad

  • Application:

    Rural Electrification / Hybrid Solar Power

  • PV Capacity:

    1.5 MW

  • Battery Capacity:

    4.2 MWh

  • Battery Chemistry:

    LiFePO4

  • Battery Configuration:

    716.8 V / 280 Ah

  • Commissioned:

    May 22, 2025

  • On-Site Deployment:

    30 Days

  • Get A Similar System

    Interested in a similar BESS for your project? Our engineers will size the right system and deliver a free ROI model within 48 hours.

    Request Free Design → Download PDF Case a Study

    Share This Case

    Free to contact us