500kW / 1MWh Energy Storage for Industrial Solar Self-Consumption and Peak Tariff Management in Spain

Valdorros, Burgos, Spain

Commissioned:2023-03-10

Client:Industrial Manufacturing Facility

  • 500 kW

    PCS Power

  • 1 MWh

    Battery Capacity

  • 400 kW

    Existing PV Array

  • AC-Coupled

    BESS

  • Front view of an open white battery storage container displaying neatly arranged battery racks and control modules.
  • Rack-mounted energy storage converters and AC power modules inside a equipment cabinet, with connected communication cables and a quality inspection report attached.

Project Overview
An industrial manufacturing facility in Valdorros (Burgos), Spain required a battery energy storage system to time-shift surplus generation from its existing 400 kW solar PV array, arbitrage volatile evening peak tariffs under the PVPC market, reduce curtailment losses, and provide uninterrupted backup for critical loads such as production lines and cold storage. The project supported Spain’s broader renewable energy integration and self-consumption objectives under RD 244/2019.
SUNPAL ESS was selected for its modular all-in-one cabinets, advanced EMS platform, and proven AC-coupled hybrid performance. The 1 MWh / 500 kW containerised BESS was designed, supplied, and commissioned as a behind-the-meter system delivering reliable daily arbitrage and operational continuity.

Challenge & Solution

Challenges

  • Surplus solar generation exceeded daytime factory consumption
  • Volatile evening tariffs increased grid electricity purchase costs
  • PV curtailment reduced the value of available solar generation
  • Critical production loads required reliable backup during grid outages

SUNPAL ESS Solutions

  • 1MWh battery stores surplus solar for peak-period consumption
  • 500kW PCS enables rapid charging and discharging for energy arbitrage
  • Intelligent EMS optimizes PV, battery, grid, and factory loads
  • Backup power supports critical production and cold-storage loads

Key Technical Specifications

ParameterSpecification
PV Capacity400 kW
PCS Rated Power500 kW
Battery Capacity1 MWh
Battery ChemistryLiFePO₄
System ConfigurationAC-Coupled
Installation TypeBehind-the-Meter
Energy Management SystemIntelligent EMS
Critical LoadsProduction Lines / Cold Storage
Electricity MarketPVPC
Regulatory ContextSpain RD 244/2019

Project Timeline

‌OCT 2022 | Project Design
SUNPAL ESS engineering team completed system sizing based on the facility's 400kW PV array, load profile, tariff structure, and critical-load requirements.

NOV 2022 | Equipment Preparation
The 500kW PCS, 1MWh LiFePO₄ battery system, EMS, and supporting electrical equipment were prepared for integration and site deployment.

‌MAR 2023 | Site Installation
The containerized BESS was installed behind the meter and electrically integrated with the existing solar PV system and industrial distribution network.

APR 2023 | System Integration
PV, battery, PCS, EMS, grid connection, and critical-load circuits were integrated to enable coordinated energy dispatch and backup operation.

MAY 2023 | Commissioned
The 500kW / 1MWh BESS completed functional testing and commissioning, enabling daily solar time-shifting, energy arbitrage, and critical-load backup.

Circular headshot photo of an Energy Manager.

Feedback from Energy Manager

"The SUNPAL ESS system gives us much greater control over the energy generated by our solar installation. We can store surplus production, use it during higher-price periods, and maintain backup power for critical operations. The combination of energy savings and operational continuity has made the project highly valuable for our facility."

Project Information

  • Client:

    Industrial Manufacturing Facility

  • Location:

    Valdorros, Burgos, Spain

  • Application:

    Industrial Solar Self-Consumption / Energy Arbitrage / Backup Power

  • Existing PV Capacity:

    400 kW

  • Battery Capacity:

    1 MWh

  • PCS Rated Power:

    500 kW

  • Battery Chemistry:

    LiFePO₄

  • Energy Management:

    Intelligent EMS

  • Commissioned:

    Mar 2023

  • Get A Similar System

    Interested in a similar BESS for your project? Our engineers will size the right system and deliver a free ROI model within 48 hours.

    Request Free Design → Download PDF Case a Study

    Share This Case

    Free to contact us